Dept. of Trans. PROGRESS Serial No. Contract No. 21-081-19-23 07-332704 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 24% Location: Federal Project: 07-LA-5-18.2/18.2 SHIM-005-3(128) Progress payment No. 005 Payment period ending: 03-20-21 WESTCOAST PUBLIC WORK INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 756,318.00 149,439.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 756,318.00 149,439.00 5. Mobilization 135,000.00 6,750.00 6. Total Work Completed 891,318.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 891,318.00 156,189.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 156,189.00