Dept. of Trans. PROGRESS Serial No. Contract No. 23-113-15-33 07-333004 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 9% Location: Federal Project: 07-LA-5-15.1/22.9 ACNH-X037(230) Progress payment No. 004 Payment period ending: 04-20-23 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 303,643.80 109,350.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 258,440.00 258,440.00 4. Earned Subject to Retention 562,083.80 367,790.00 5. Mobilization 511,977.00 511,977.00 6. Total Work Completed 815,620.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,074,060.80 879,767.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 879,767.00