Dept. of Trans. PROGRESS Serial No. Contract No. 22-144-12-14 07-333204 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 23% Location: Federal Project: 07-KER-5-0.6/1.2 NONE Progress payment No. 002 Payment period ending: 05-20-22 GENUINE ENGINEERING INC 13306 INDIAN BOW CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 358,822.46 83,334.46 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 358,822.46 83,334.46 5. Mobilization 75,000.00 0.00 6. Total Work Completed 433,822.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 433,822.46 83,334.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 83,334.46