Dept. of Trans. PROGRESS Serial No. Contract No. 22-167-11-33 07-333204 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 37% Location: Federal Project: 07-KER-5-0.6/1.2 NONE Progress payment No. 003 Payment period ending: 06-20-22 GENUINE ENGINEERING INC 13306 INDIAN BOW CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,055.63 262,233.17 2. a. Extra Work 48,649.77 48,649.77 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 669,705.40 310,882.94 5. Mobilization 95,000.00 20,000.00 6. Total Work Completed 764,705.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 764,705.40 330,882.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 330,882.94