Dept. of Trans. PROGRESS Serial No. Contract No. 23-079-21-44 07-335004 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 88% Location: Federal Project: 07-LA-110-0.7/8.8 NONE Progress payment No. 009 Payment period ending: 03-20-23 SELECT ELECTRIC INC 2790 BUSINESS PARK DR VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 576,776.46 26,814.04 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 576,776.46 26,814.04 5. Mobilization 38,542.00 0.00 6. Total Work Completed 615,318.46 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 613,318.46 26,814.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,814.04