Dept. of Trans. PROGRESS Serial No. Contract No. 23-114-09-36 07-335004 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 93% Location: Federal Project: 07-LA-110-0.7/8.8 NONE Progress payment No. 010 Payment period ending: 04-20-23 SELECT ELECTRIC INC 2790 BUSINESS PARK DR VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 595,433.05 18,656.59 2. a. Extra Work 58,966.26 58,966.26 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 654,399.31 77,622.85 5. Mobilization 38,542.00 0.00 6. Total Work Completed 692,941.31 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 690,941.31 77,622.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,622.85