Dept. of Trans. PROGRESS Serial No. Contract No. 22-354-12-54 07-335304 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 22% Location: Federal Project: 07-LA-10-42.3/48.3 ACIM-010-1(856) Progress payment No. 003 Payment period ending: 12-20-22 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,461.75 93,724.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 291,307.00 0.00 4. Earned Subject to Retention 391,768.75 93,724.25 5. Mobilization 183,750.00 0.00 6. Total Work Completed 284,211.75 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 575,518.75 103,724.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 103,724.25