Dept. of Trans. PROGRESS Serial No. Contract No. 25-052-10-02 07-336004 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 95% Location: Federal Project: 07-VEN-118-R1.4/1.8 ACNH-P118(70) Progress payment No. 022 Payment period ending: 02-20-25 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,578,750.10 25,345.50 2. a. Extra Work 115,579.44 0.00 b. Adustment Comp. 124,027.73 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,818,357.27 25,345.50 5. Mobilization 481,541.40 0.00 6. Total Work Completed 5,299,898.67 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,299,898.67 25,345.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,345.50