Dept. of Trans. PROGRESS Serial No. Contract No. 23-111-14-11 07-336504 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 34% Location: Federal Project: 07-LA-110-3.9/5.9 ACIM-1101(849) Progress payment No. 008 Payment period ending: 04-20-23 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 738,865.85 214,527.85 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 738,865.85 214,527.85 5. Mobilization 85,000.00 4,250.00 6. Total Work Completed 823,865.85 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 823,865.85 228,777.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 228,777.85