Dept. of Trans. PROGRESS Serial No. Contract No. 23-143-15-10 07-336504 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 34% Location: Federal Project: 07-LA-110-3.9/5.9 ACIM-1101(849) Progress payment No. 009 Payment period ending: 05-20-23 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 783,530.85 44,665.00 2. a. Extra Work 46,694.00 46,694.00 b. Adustment Comp. 31,600.00 31,600.00 3. Materials on Hand 4. Earned Subject to Retention 861,824.85 122,959.00 5. Mobilization 85,000.00 0.00 6. Total Work Completed 946,824.85 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 946,824.85 122,959.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 122,959.00