Dept. of Trans. FINAL Serial No. Contract No. 23-292-08-45 07-337604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-14-28.9/29.2 NONE Progress payment No. 026 Payment period ending: 01-20-23 SEMA CONSTRUCTION INC 9810 SCRIPPS LAKE DR #C SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,906,766.78 31,724.85 2. a. Extra Work 40,777.35 0.00 b. Adustment Comp. 235,956.45 -4,683.53 3. Materials on Hand 4. Earned Subject to Retention 4,183,500.58 27,041.32 5. Mobilization 355,346.51 0.00 6. Total Work Completed 4,538,847.09 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,538,847.09 27,041.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,041.32