Dept. of Trans. PROGRESS Serial No. Contract No. 23-360-13-30 07-337804 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 24% Location: Federal Project: 07-LA-101-S0.0/R17.1 NONE Progress payment No. 005 Payment period ending: 12-20-23 JFL ELECTRIC INC 8257 COMPTON AVENUE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 733,781.00 101,798.00 2. a. Extra Work 35,470.82 490.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 769,251.82 102,288.00 5. Mobilization 337,500.00 112,500.00 6. Total Work Completed 1,106,751.82 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,106,751.82 214,788.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 214,788.00