Dept. of Trans. PROGRESS Serial No. Contract No. 21-111-15-11 07-338004 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 78% Location: Federal Project: 07-LA-5-20.8/20.8 NONE Progress payment No. 004 Payment period ending: 04-20-21 LANDSCAPE SUPPORT SERVICES INC 12610 SATICOY ST SOUTH N HOLLYWOOD CA 91605 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 453,375.71 186,040.61 2. a. Extra Work 39,734.55 18,841.45 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 493,110.26 204,882.06 5. Mobilization 59,567.00 2,978.35 6. Total Work Completed 552,677.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 552,677.26 207,860.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 207,860.41