Dept. of Trans. PROGRESS Serial No. Contract No. 25-164-17-10 07-338604 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 40% Location: Federal Project: 07-VAR-91-R6.1/R20.7 ACNH-X037(231) Progress payment No. 015 Payment period ending: 06-20-25 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,056,598.18 224,090.81 2. a. Extra Work 467,087.18 24,565.07 b. Adustment Comp. -172,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,351,685.36 248,655.88 5. Mobilization 1,600,000.00 0.00 6. Total Work Completed 10,951,685.36 7. Deductions -302,710.75 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,648,974.61 248,655.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,655.88