Dept. of Trans. PROGRESS Serial No. Contract No. 22-115-11-04 07-339804 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 72% Location: Federal Project: 07-LA-1-6.0/6.0 HSTG-P001(667) Progress payment No. 004 Payment period ending: 04-20-22 CROSSTOWN ELECTRICAL & DATA INC 5454 DIAZ ST IRWINDALE CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 187,259.21 26,118.94 2. a. Extra Work 17,911.35 17,911.35 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 205,170.56 44,030.29 5. Mobilization 10,000.00 0.00 6. Total Work Completed 215,170.56 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 215,170.56 44,030.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,030.29