Dept. of Trans. PROGRESS Serial No. Contract No. 22-021-16-47 07-341704 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 83% Location: Federal Project: 07-LA-1-2.8/2.8 SSTG-P001(668) Progress payment No. 005 Payment period ending: 01-20-22 INTERNATIONAL LINE BUILDERS, INC. PO BOX 3039 RIVERSIDE CA 92519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 311,840.19 0.00 2. a. Extra Work 11,627.53 3,080.32 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 323,467.72 3,080.32 5. Mobilization 14,805.00 0.00 6. Total Work Completed 338,272.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 338,272.72 3,080.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,080.32