Dept. of Trans. PROGRESS Serial No. Contract No. 23-233-11-04 07-343204 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 17% Location: Federal Project: 07-LA-405-48.0/48.5 ACIM-405-3(4) Progress payment No. 007 Payment period ending: 08-20-23 SUKUT CONSTRUCTION LLC 4010 W CHANDLER AVE SANTA ANA CA 92704 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,892,436.50 3,399,990.50 2. a. Extra Work 17,706.74 0.00 b. Adustment Comp. 3. Materials on Hand 95,601.71 95,601.71 4. Earned Subject to Retention 11,005,744.95 3,495,592.21 5. Mobilization 1,000,000.00 50,000.00 6. Total Work Completed 11,910,143.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,005,744.95 3,545,592.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,545,592.21