Dept. of Trans. PROGRESS Serial No. Contract No. 24-292-15-23 07-343204 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 66% Location: Federal Project: 07-LA-405-48.0/48.5 ACIM-405-3(4) Progress payment No. 021 Payment period ending: 10-20-24 SUKUT CONSTRUCTION LLC 4010 W CHANDLER AVE SANTA ANA CA 92704 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,148,502.05 346,390.50 2. a. Extra Work 1,283,581.63 7,770.97 b. Adustment Comp. 29,931.01 15,661.40 3. Materials on Hand 4. Earned Subject to Retention 17,462,014.69 369,822.87 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 18,462,014.69 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,462,014.69 369,822.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 369,822.87