Dept. of Trans. PROGRESS Serial No. Contract No. 25-079-11-45 07-347004 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 31% Location: Federal Project: 07-LA-710-9.6/T32.1 NONE Progress payment No. 003 Payment period ending: 03-20-25 DOJA INC 5050 MISSION BLVD ONTARIO CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 624,812.00 188,000.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 624,812.00 188,000.00 5. Mobilization 198,750.00 66,250.00 6. Total Work Completed 823,562.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 823,562.00 254,250.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 254,250.00