Dept. of Trans. PROGRESS Serial No. Contract No. 26-083-10-22 07-347904 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 23% Location: Federal Project: 07-LA-405-31.2/41.4 ACIM-4053(853) Progress payment No. 010 Payment period ending: 03-20-26 RASMUSSEN/VANGUARD 28548 LIVINGSTON AVE VALENCIA CA 91355 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,881,797.45 2,429,761.30 2. a. Extra Work 114,845.07 1,985.10 b. Adustment Comp. 3. Materials on Hand 323,544.38 323,544.38 4. Earned Subject to Retention 29,320,186.90 2,755,290.78 5. Mobilization 9,500,000.00 0.00 6. Total Work Completed 38,496,642.52 7. Deductions -88,409.84 743,317.15 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,731,777.06 3,498,607.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,498,607.93