Dept. of Trans. PROGRESS Serial No. Contract No. 25-105-17-48 07-348404 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 25% Location: Federal Project: 07-VEN-23-0.0/R3.3 ACST-P023(42) 07-VEN-23-T11.5/24.2 Progress payment No. 003 Payment period ending: 04-20-25 ACCU CONSTRUCTION INC 14751 PLAZA DRIVE #L TUSTIN CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 267,638.00 96,407.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 267,638.00 96,407.40 5. Mobilization 135,000.00 0.00 6. Total Work Completed 402,638.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 402,638.00 96,407.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 96,407.40