Dept. of Trans. PROGRESS Serial No. Contract No. 25-164-18-02 07-348404 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 50% Location: Federal Project: 07-VEN-23-0.0/R3.3 ACST-P023(42) 07-VEN-23-T11.5/24.2 Progress payment No. 005 Payment period ending: 06-20-25 ACCU CONSTRUCTION INC 14751 PLAZA DRIVE #L TUSTIN CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 507,703.00 101,420.00 2. a. Extra Work 2,250.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 509,953.00 101,420.00 5. Mobilization 171,000.00 0.00 6. Total Work Completed 680,953.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 680,953.00 101,420.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 101,420.00