Dept. of Trans. PROGRESS Serial No. Contract No. 24-325-09-12 07-348904 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 53% Location: Federal Project: 07-LA-39-20.7/20.7 NONE Progress payment No. 005 Payment period ending: 11-20-24 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 535,224.50 253,860.00 2. a. Extra Work 42,311.90 42,311.90 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 577,536.40 296,171.90 5. Mobilization 137,978.00 29,048.00 6. Total Work Completed 715,514.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 715,514.40 325,219.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 325,219.90