Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-17-00 07-349104 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 57% Location: Federal Project: 07-VAR-210-R43.9/R46.7 NONE Progress payment No. 006 Payment period ending: 08-20-25 INTERNATIONAL LINE BUILDERS, INC. 3955 TEMESCAL CYN RD CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,298,759.12 578,850.88 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,298,759.12 578,850.88 5. Mobilization 180,500.00 0.00 6. Total Work Completed 1,479,259.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,479,259.12 578,850.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 578,850.88