Dept. of Trans. PROGRESS Serial No. Contract No. 25-202-10-42 07-349904 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 21% Location: Federal Project: 07-LA-710-6.0/14.1 ACIM-7101(845) Progress payment No. 006 Payment period ending: 07-20-25 WESTCOAST PUBLIC WORKS INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,722,351.19 460,072.24 2. a. Extra Work 1,370.58 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,723,721.77 460,072.24 5. Mobilization 501,102.20 0.00 6. Total Work Completed 2,224,823.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,224,823.97 460,072.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 460,072.24