Dept. of Trans. PROGRESS Serial No. Contract No. 25-296-16-11 07-351114 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 18% Location: Federal Project: 07-VAR NONE Progress payment No. 005 Payment period ending: 10-20-25 CALPROMAX ENGINEERING INC 650 N ROSE DRIVE #186 PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 391,320.00 298,920.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 434,005.00 0.00 4. Earned Subject to Retention 825,325.00 298,920.00 5. Mobilization 405,000.00 0.00 6. Total Work Completed 796,320.00 7. Deductions -271,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 959,280.00 298,920.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 298,920.00