Dept. of Trans. PROGRESS Serial No. Contract No. 25-325-17-15 07-351124 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 20% Location: Federal Project: 07-VAR NONE Progress payment No. 005 Payment period ending: 11-20-25 SELECT ELECTRIC INC 1700 E VIA BURTON ANAHEIM CA 92806 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 916,102.55 288,048.95 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 916,102.55 288,048.95 5. Mobilization 204,693.00 0.00 6. Total Work Completed 1,120,795.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,120,795.55 288,048.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 288,048.95