Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-14-04 07-351804 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 99% Location: Federal Project: 07-LA-5-17.9/18.0 CIMG-005-3(130) Progress payment No. 010 Payment period ending: 09-20-24 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 620,130.64 3,642.50 2. a. Extra Work 32,582.18 32,582.18 b. Adustment Comp. 37,640.02 0.00 3. Materials on Hand 4. Earned Subject to Retention 690,352.84 36,224.68 5. Mobilization 55,000.00 0.00 6. Total Work Completed 745,352.84 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 745,352.84 36,224.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,224.68