Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-014-16-05 07-351804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-5-17.9/18.0 CIMG-005-3(130) Progress payment No. 011 Payment period ending: 11-12-24 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 649,246.00 29,115.36 2. a. Extra Work 32,582.18 0.00 b. Adustment Comp. 37,640.02 0.00 3. Materials on Hand 4. Earned Subject to Retention 719,468.20 29,115.36 5. Mobilization 55,000.00 0.00 6. Total Work Completed 774,468.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 774,468.20 29,115.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,115.36