Dept. of Trans. PROGRESS Serial No. Contract No. 24-262-09-41 07-352004 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 91% Location: Federal Project: 07-LA-1-4.8/6.6 NONE Progress payment No. 006 Payment period ending: 09-12-24 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 711,699.42 115,120.13 2. a. Extra Work 10,230.94 0.00 b. Adustment Comp. 3. Materials on Hand 149,918.42 0.00 4. Earned Subject to Retention 871,848.78 115,120.13 5. Mobilization 109,250.00 0.00 6. Total Work Completed 831,180.36 7. Deductions -86,250.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 894,848.78 115,120.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,120.13