Dept. of Trans. PROGRESS Serial No. Contract No. 25-165-12-25 07-355104 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 28% Location: Federal Project: 07-VAR-105-R2.1/R2.1 ACIM-X037(233) Progress payment No. 006 Payment period ending: 06-20-25 ALDRIDGE ELECTRIC INC 844 E ROCKLAND RD LIBERTYVILLE IL 60048 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,970,281.46 4,252,917.08 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 1,221,285.02 -937,543.31 4. Earned Subject to Retention 10,191,566.48 3,315,373.77 5. Mobilization 6. Total Work Completed 8,970,281.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,191,566.48 3,315,373.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,315,373.77