Dept. of Trans. PROGRESS Serial No. Contract No. 25-204-07-01 07-355104 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 33% Location: Federal Project: 07-VAR-105-R2.1/R2.1 ACIM-X037(233) Progress payment No. 007 Payment period ending: 07-20-25 ALDRIDGE ELECTRIC INC 844 E ROCKLAND RD LIBERTYVILLE IL 60048 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,922,038.95 3,951,757.49 2. a. Extra Work 13,000.00 13,000.00 b. Adustment Comp. 52,891.66 52,891.66 3. Materials on Hand 39,010.36 -1,182,274.66 4. Earned Subject to Retention 13,026,940.97 2,835,374.49 5. Mobilization 6. Total Work Completed 12,987,930.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,026,940.97 2,835,374.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,835,374.49