Dept. of Trans. PROGRESS Serial No. Contract No. 25-202-16-18 07-356604 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 11% Location: Federal Project: 07-LA-605-R10.2/20.2 ACIM-6052(88) Progress payment No. 011 Payment period ending: 07-20-25 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,862,515.09 1,467,392.06 2. a. Extra Work 589,010.50 99,360.75 b. Adustment Comp. 3. Materials on Hand 1,076,067.84 127,943.08 4. Earned Subject to Retention 20,527,593.43 1,694,695.89 5. Mobilization 11,550,000.00 0.00 6. Total Work Completed 31,001,525.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,077,593.43 1,694,695.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,694,695.89