Dept. of Trans. PROGRESS Serial No. Contract No. 25-262-12-07 07-356604 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 12% Location: Federal Project: 07-LA-605-R10.2/20.2 ACIM-6052(88) Progress payment No. 013 Payment period ending: 09-20-25 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,738,036.49 3,681,599.40 2. a. Extra Work 1,103,351.44 220,300.36 b. Adustment Comp. 3. Materials on Hand 933,207.45 0.00 4. Earned Subject to Retention 27,774,595.38 3,901,899.76 5. Mobilization 11,550,000.00 0.00 6. Total Work Completed 38,391,387.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 39,324,595.38 3,901,899.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,901,899.76