Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-09-16 07-357004 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 20% Location: Federal Project: 07-LA-105-R4.3/R5.0 HSIM-1053(993) Progress payment No. 006 Payment period ending: 09-20-24 POLO ENGINEERING INC 30758 SLOAN CANYON RD CASTAIC CA 91384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 86,035.25 36,670.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 47,028.65 47,028.65 4. Earned Subject to Retention 133,063.90 83,698.90 5. Mobilization 101,550.00 101,550.00 6. Total Work Completed 187,585.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 234,613.90 185,248.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 185,248.90