Dept. of Trans. PROGRESS Serial No. Contract No. 25-052-14-03 07-357304 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 64% Location: Federal Project: 07-LA-5-6.6/13.1 ACIM-052(37) Progress payment No. 018 Payment period ending: 02-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,844,281.27 384,100.00 2. a. Extra Work 2,299,075.58 0.00 b. Adustment Comp. 3. Materials on Hand 10,499.00 -57,420.00 4. Earned Subject to Retention 7,153,855.85 326,680.00 5. Mobilization 902,500.00 0.00 6. Total Work Completed 8,045,856.85 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,056,355.85 326,680.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 326,680.00