Dept. of Trans. PROGRESS Serial No. Contract No. 25-325-16-07 07-357304 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 100% Location: Federal Project: 07-LA-5-6.6/13.1 ACIM-052(37) Progress payment No. 027 Payment period ending: 11-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,855,596.28 352,692.60 2. a. Extra Work 3,185,159.44 686,322.13 b. Adustment Comp. 3. Materials on Hand 0.00 -31,722.00 4. Earned Subject to Retention 21,040,755.72 1,007,292.73 5. Mobilization 950,000.00 0.00 6. Total Work Completed 21,990,755.72 7. Deductions -12,300.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,978,455.72 1,007,292.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,007,292.73