Dept. of Trans. PROGRESS Serial No. Contract No. 26-051-16-52 07-357304 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 100% Location: Federal Project: 07-LA-5-6.6/13.1 ACIM-052(37) Progress payment No. 030 Payment period ending: 02-20-26 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,445,413.68 320,632.40 2. a. Extra Work 3,717,375.52 9,378.73 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 22,162,789.20 330,011.13 5. Mobilization 950,000.00 0.00 6. Total Work Completed 23,112,789.20 7. Deductions -12,300.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,100,489.20 330,011.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 330,011.13