Dept. of Trans. PROGRESS Serial No. Contract No. 25-107-13-59 07-358404 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 41% Location: Federal Project: 07-LA-10-R4.7/18.9 PTIM-101(859) Progress payment No. 003 Payment period ending: 04-20-25 YAKAR 689 EAST SAN BERNARDINO RD COVINA CA 91723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 167,825.00 62,500.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 167,825.00 62,500.00 5. Mobilization 122,500.00 122,500.00 6. Total Work Completed 290,325.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 290,325.00 185,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 185,000.00