Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-13-46 07-370704 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 56% Location: Federal Project: 07-LA-126-R2.4/2.4 HSNH-P126(59) Progress payment No. 002 Payment period ending: 09-20-24 POLO ENGINEERING INC 30758 SLOAN CANYON RD CASTAIC CA 91384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 568,013.00 193,509.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 568,013.00 193,509.00 5. Mobilization 35,962.00 0.00 6. Total Work Completed 603,975.00 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 583,975.00 173,509.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,509.00