Dept. of Trans. PROGRESS Serial No. Contract No. 23-115-11-40 07-384604 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 42% Location: Federal Project: 07-LA-10-0.1/13.3 NONE Progress payment No. 003 Payment period ending: 04-20-23 BOSCO CONSTRUCTORS INC 21353 MAYALL ST CHATSWORTH CA 91311 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 516,676.60 145,761.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 516,676.60 145,761.60 5. Mobilization 202,500.00 67,500.00 6. Total Work Completed 719,176.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 719,176.60 213,261.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 213,261.60