Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-18-11 07-385104 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 34% Location: Federal Project: 07-VEN-118-R23.5/R30.5 NONE Progress payment No. 019 Payment period ending: 08-20-25 MARTINEZ LANDSCAPE CO INC 12357 SAN FERNANDO RD SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,107,248.70 0.00 2. a. Extra Work 59,285.57 31,731.84 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,166,534.27 31,731.84 5. Mobilization 327,618.58 0.00 6. Total Work Completed 2,494,152.85 7. Deductions -74,837.00 -29,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,419,315.85 2,731.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,731.84