Dept. of Trans. PROGRESS Serial No. Contract No. 24-081-19-13 07-385804 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 6% Location: Federal Project: 07-LA-710-13.8/R15.3 NONE Progress payment No. 001 Payment period ending: 03-20-24 WESTCOAST PUBLIC WORKS INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,345.00 53,345.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 53,345.00 53,345.00 5. Mobilization 6. Total Work Completed 53,345.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 53,345.00 53,345.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,345.00