Dept. of Trans. PROGRESS Serial No. Contract No. 24-142-18-20 07-385804 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 12% Location: Federal Project: 07-LA-710-13.8/R15.3 NONE Progress payment No. 003 Payment period ending: 05-20-24 WESTCOAST PUBLIC WORKS INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 515,577.00 317,457.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 515,577.00 317,457.50 5. Mobilization 223,947.75 74,649.25 6. Total Work Completed 739,524.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 739,524.75 392,106.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 392,106.75