Dept. of Trans. PROGRESS Serial No. Contract No. 23-233-10-08 07-386004 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 4% Location: Federal Project: 07-LA-10-18.8/20.5 NONE Progress payment No. 002 Payment period ending: 08-20-23 WESTCOAST PUBLIC WORKS INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,065.00 39,065.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 57,065.00 39,065.00 5. Mobilization 61,320.00 61,320.00 6. Total Work Completed 118,385.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 118,385.00 100,385.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,385.00