Dept. of Trans. PROGRESS Serial No. Contract No. 25-262-12-54 07-398404 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 07-LA-10-28.5/30.8 NONE Progress payment No. 009 Payment period ending: 09-20-25 MARTINEZ LANDSCAPE CO INC 12357 SAN FERNANDO RD SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 913,183.75 60,013.25 2. a. Extra Work 6,812.78 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 919,996.53 60,013.25 5. Mobilization 20,000.00 0.00 6. Total Work Completed 939,996.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 939,996.53 60,013.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 60,013.25