Dept. of Trans. PROGRESS Serial No. Contract No. 25-057-10-50 07-398504 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 22% Location: Federal Project: 07-LA-105-R2.1/R2.5 NONE Progress payment No. 002 Payment period ending: 02-20-25 LANDSCAPE SUPPORT SERVICES INC 12610 SATICOY ST SOUTH N HOLLYWOOD CA 91605 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 229,505.76 228,556.76 2. a. Extra Work 13,034.80 13,034.80 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 242,540.56 241,591.56 5. Mobilization 35,513.00 35,513.00 6. Total Work Completed 278,053.56 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 278,053.56 277,104.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 277,104.56