Dept. of Trans. PROGRESS Serial No. Contract No. 09-022-15-04 07-3N7904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 62% 07-VEN-1-12.7/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 01-20-09 T D S ENGINEERING 1014 S WESTLAKE BLVD #14136 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 279,665.73 46,784.77 2.a. Extra Work 8,388.39 8,388.39 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 288,054.12 55,173.16 5. Mobilization 10,000.00 0.00 6. Total Work Completed 298,054.12 7. Deductions 8. a.Contract Retentions -14,402.71 -2,758.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 283,651.41 52,414.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,414.50