Dept. of Trans. PROGRESS Serial No. Contract No. 19-142-11-41 07-3P6804 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 89% Location: Federal Project: 07-LA-210-39.7/39.7 NONE Progress payment No. 010 Payment period ending: 05-20-19 ALFARO COMMUNICATIONS CONSTRUCTION INC 620 S BRADFIELD AVE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 469,289.13 1,521.00 2. a. Extra Work 16,821.40 0.00 b. Adustment Comp. 55,664.98 0.00 3. Materials on Hand 4. Earned Subject to Retention 541,775.51 1,521.00 5. Mobilization 9,000.00 0.00 6. Total Work Completed 550,775.51 7. Deductions 0.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 550,775.51 8,521.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,521.00