Dept. of Trans. PROGRESS Serial No. Contract No. 15-324-10-10 07-3P7004 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 42% Location: Federal Project: 07-VEN-33-11.3/11.3 NONE Progress payment No. 005 Payment period ending: 11-20-15 MGP CONSTRUCTION 111 N. GROVE AVE. UPLAND CA 91786 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 392,334.69 40,512.84 2. a. Extra Work 3,461.76 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 395,796.45 40,512.84 5. Mobilization 6. Total Work Completed 395,796.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 395,796.45 40,512.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,512.84